hall contracting

The Bridge
4:13 pm
Thu May 24, 2012

Bridge to Re-Open Today

KYTC

The U.S. 68/KY U.S. 68/KY 80 Eggners Ferry Bridge repairs have been completed and state officials have sent word the span is to be reopened today.

9:00 UPDATE

As Kentucky Transportation officials and contractors finalize work to re-open the Eggners Ferry Bridge today, the span will be open to pedestrian and bike traffic beginning this morning at nine.  KYTC spokesman Keith Todd says anyone visiting the bridge should park off of the roadway and will still need to be careful as crews continue clean-up and finishing work.  There is an event scheduled for noon in the middle of the new span, and visitors will need to be off the bridge by 1 p.m.  Officials are hoping to have the crossing open to vehicle traffic at that time.  Kentucky Governor Steve Beshear says he’s pleased repairs will be completed ahead of the May 27th deadline and by a Kentucky company.

Read more
The Bridge
8:54 am
Thu May 24, 2012

Eggners Ferry Bridge Repairs are On Track

Kentucky Transportation Cabinet

The Eggners Ferry Bridge may open a few hours ahead of schedule this Memorial Day weekend, but officials say don't plan on it. Yesterday, crews worked on the curbs and guardrails. 

Read more
The Bridge
7:23 am
Mon May 21, 2012

Eggners Ferry Bridge Nearly Whole Again

Kentucky Transportation Cabinet

Construction workers poured the concrete deck for the replacement span of the US 68/KY 80 Eggners Ferry Bridge yesterday morning. 

Read more
The Bridge
9:07 am
Tue May 15, 2012

Eggners Ferry Bridge Span Makes it Down

Kentucky Transportation Cabinet

A replacement span for a collapsed portion of the US 68/KY 80 Eggners Ferry Bridge is now at the bridge site. A 3-barge flotilla took just over 5 hours yesterday to navigate the 30 miles from the Eddyville Riverport, down Lake Barkley, through the LBL Canal, and up Kentucky Lake. 

Read more
The Bridge
8:50 am
Mon May 14, 2012

New Eggners Ferry Bridge Span Moving to Site Today

Kentucky Transportation Cabinet

Kentucky Transportation Officials say it will likely be sometime today before the new span for the Eggners Ferry Bridge and the two cranes required to lift it into place can be moved from the Eddyville Riverport to the bridge site.  

Read more
The Bridge
4:25 pm
Thu May 10, 2012

Eggners Ferry Replacement Span Loaded on Barges for Transport

Hall Contracting successfully moved a replacement span for the US 68/KY 80 Eggners Ferry Bridge from an assembly area onto a barge today.  The 4-hour transfer of the 300 ton steel truss was the first step toward getting the new span moved to the bridge.

Read more
The Bridge
4:52 pm
Wed May 9, 2012

Bridge Span Will Make Trip Up River In Coming Days

KYTC

Engineers are optimistic they will be able to load and move the replacement span of the Eggners Ferry Bridge  by barge on Friday or Saturday, but contractors note there are still plenty of details to work through.

Read more
The Bridge
3:49 pm
Tue May 8, 2012

Initial Construction Phase for Eggners Ferry Repairs Nearly Complete

From the Kentucky Transportation Cabinet:

Hall Contracting of Kentucky reports the initial phase of steel assembly as part of efforts to place a new span on the US 68/KY 80 Eggners Ferry Bridge at Aurora is nearing completion.

Read more
The Bridge
3:10 pm
Tue April 24, 2012

Beshear Explains Staging for Bridge Repair

The next step in the repair project for the Eggners Ferry Bridge over Kentucky Lake is underway.

Read more
The Bridge
4:39 pm
Mon April 23, 2012

Beshear to Visit West KY For Update on Eggners Ferry

Governor Steve Beshear will be in Eddyville Tuesday with an update on repair work to the Eggners Ferry Bridge. Beshear along with Chief District Engineer Jim Lefevre and Tom Roberts of Hall Contracting will be at the Lyon County Riverport Authority at 1:30.

It’s likely they’ll discuss staging for repair work on the bridge that lost a 300 foot span after a cargo ship crashed into the road deck in January.

Pages