Gov. Announces Progress Toward Replacing Lakes Bridges

Credit KyTC

Kentucky Transportation Cabinet crews are taking the first step toward replacing the Eggners Ferry Bridge by clearing brush ahead of constructing a secondary bridge to span a lagoon adjacent to Kentucky Lake.

Gov. Steve Beshear says construction of the lagoon bridge is “giant step” toward replacing the 81-year-old existing structure and building new bridges over the lakes. Jim Smith Construction, LLC., has a 420-day contract to complete the $24 million project.

Kentucky Transportation Cabinet Spokesman Keith Todd says work on the lagoon bridge will move the department closer to pier construction of the larger bridge that carries US 68/KY 80 over the lakes to Land Between the Lakes.