Nuclear Regulatory Commission

WKMS File Photo

The Nuclear Regulatory Commission is holding a public meeting tonight to discuss the results of its special inspection into uranium hexafluoride leak at the Honeywell Metropolis plant in August.


Honeywell’s Metropolis plant restarts production today, 18 days after a gas leak at the facility.

On the evening of Oct 26, employees there reported a uranium hexafluoride gas (UF-6) leak that put the plant into emergency shutdown mode.

A company investigation determined the leak was internal and caused by mechanical failure near the end of the production process.

GE Hitachi's Global Laser Enrichment is seeking approval from the Nuclear Regulatory Commission to use the Paducah Gaseous Diffusion Plant.

GLE has been in negotiations with the Department of Energy since late November for use of the site and the depleted uranium stored there.

A recent congressional study shows Tennessee's nuclear plants had a total of 258 safety violations between 2000 and 2012.

The Associated Press obtained a copy of the Government Accountability Office report that's awaiting release. Nuclear Regulatory Commission figures cited in the report show the Sequoyah plant in Soddy-Daisy had 125 violations, of which all but two were lower-level violations.

file photo

Honeywell's Metropolis plant can resume full operations after receiving the go ahead from the Nuclear Regulatory Commission. The plant which converts uranium or to uranium-hexafluoride closed last year after failing to meet standards for natural disaster preparedness. 228 employees had been without work while the plant addressed the infrastructure needs. 

The Southern Illinoisan

The Honeywell Uranium Processing Facility is allowing some plant workers to leave while law enforcement and plant management continue investigating a report of an explosive device in the plant.

Honeywell went on lockdown after receiving the report this afternoon. Honeywell spokesman Peter Dalpe said law enforcement and members of the state bomb squad are on scene. 

Honeywell Sets Potential June Plant Restart Date

Nov 1, 2012
file photo

Honeywell officials say they could restart production at the Metropolis, Illinois nuclear fuel refinery next June. The plant shut down in July this year after a Nuclear Regulatory Commission inspection found a need for safety upgrades. The move laid off 212 union workers. Honeywell spokesman John McCarthy says a staff of a little over a hundred remains at the facility. Plant officials hope to begin recalling workers for retraining and certification in April.

Nuclear Regulatory Commission Meeting with Honeywell

Aug 22, 2012

The Nuclear Regulatory Commission plans talks next week in Atlanta with executives from Honeywell’s Metropolis, Ill., plant. The Paducah Sun reports they’ll meet Monday to discuss apparent violations associated with the company’s alleged failure to identify the kinds of accidents significant earthquakes or tornadoes might cause. NRC Public Affairs Officer Roger Hannah says the agency is especially concerned about the potential release of large amounts of uranium hexafluoride.   The meeting will review information presented by the plant.

file photo

United Steelworkers officials who represent the hourly workers at the Honeywell nuclear facility in Metropolis say they were not notified beforehand of the company’s decision to not re-open the plant to perform upgrades. 

WKMS File Photo

The Honeywell nuclear facility in Metropolis will not restart production until they reach an agreement on facility upgrades with the US Nuclear Regulatory Commission.